Capacity Reconciliation Sprint (Delivery)
A sequence with 7 steps: Pull current allocation data from your scheduling platform.
By InnovaAI ResearchPublished
What are the steps?
Capacity Reconciliation Sprint (Delivery)
- 01
Pull current allocation data from your scheduling platform
Export scheduled hours per team member and per project from tools like Float or Runn, covering the next two weeks.
- 02
Compare scheduled hours against actual time logged
Use time tracking data from Toggl or Everhour to identify discrepancies between planned and actual effort, flagging any variance above 10%.
- 03
Review project pipeline for upcoming demand shifts
Check for new client wins, scope changes, or delays that alter resource requirements, and note any projects at risk of overrunning.
- 04
Identify underutilized or overbooked team members
Calculate each person's utilization rate, targeting 70-85% billable; flag anyone below 60% or above 90% for immediate action.
- 05
Reallocate resources to balance workload across projects
Move assignments to match skills with demand, prioritizing critical deadlines and client commitments over internal preferences.
- 06
Communicate updated schedules to the team and stakeholders
Send a brief summary of changes, including new assignments and any adjustments to project timelines, to ensure everyone is aligned.
- 07
Document lessons learned and adjust forecasting assumptions
Note recurring patterns in estimation errors or capacity gaps, and update your planning templates to improve future accuracy.