Client Hosting Migration Cutover (Onboarding)
A sequence with 6 steps: Freeze the client's DNS and content changes 48 hours before cutover.
By InnovaAI ResearchPublished
What are the steps?
Client Hosting Migration Cutover (Onboarding)
- 01
Freeze the client's DNS and content changes 48 hours before cutover
Record current TTL values for the A, MX, and CNAME records, then lower TTLs to 300 seconds so the switch propagates quickly. Ask the client to pause publishing so no content is written to the old host after the snapshot.
- 02
Capture a full inventory of the existing environment
List every site, database, mail account, cron job, SSL certificate, and third-party integration on the old host. Agencies that skip this step most often lose email routing or form submissions after cutover.
- 03
Stage the site on the destination platform and test it against the staging URL
Confirm PHP version, database charset, and file permissions match production. Managed WordPress platforms such as WPX include free migrations, but the agency still owns verification of forms, checkout, and redirects.
- 04
Run the cutover window with a rollback owner assigned
Name one person who can revert DNS within the window if error rates or broken pages appear. Keep the old host active for at least 14 days so the rollback path stays open.
- 05
Verify mail, SSL, redirects, and uptime from three external locations
Send test messages in both directions, confirm the certificate chain is valid, and check that legacy URLs return 301 responses to new paths. Log results in the client record before signing off.
- 06
Issue the client handoff note and set the retainer billing start date
Document which hosting tier, backup schedule, and support channel now apply. Shops reselling hosting under white-label programs such as Krystal's reseller offering should record which party holds the account login and renewal date.